collapse Primary Category : Aviation ‎(6)
  
Recommended2017-02-14-094amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Statistics have shown that the airport activity continues to increase. The presence of Penn State's research center, athletics, and tourist connections further boost the need for improvements to constructing an access road in conjunction with additional parking. 
02
  
Recommended2017-06-46-070amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
With Heritage Field being classified as an intermediate airport and serves as a reliever for PHL, construction of 5 new hangars and a corporate terminal will boost operations further to meet the needs of the region. Also, the project would be over 50% funded by private sector.
06
  
Recommended2017-06-46-170amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
The growth of the Cirrus aircraft in a few years have exceeded the space to store aircrafts in hangars. Having an avionics and maintenance repair center will further attract the GA aircraft which will boost the local economy.
06
  
Recommended2017-08-36-209amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Construction of the avionics center will bring additional business into the airport. Additional jobs will be created too.
08
  
Recommended2017-11-02-213amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Similar SOW resulted in last year's $1.4M MMA (multimodal aviation grant). Keeping pavements in the state of good repair is essential to sustain activity. Also, this SOW is not typically eligible with FAA Airport Improvement Project funds. 
11
  
Recommended2017-11-02-216amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Project is critical to preserve the pavement of an apron for a Corporate facility.
11
collapse Primary Category : Bicycle/Pedestrian ‎(55)
  
Recommended2017-02-14-142djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
02
  
Recommended2017-02-17-120dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Linked to Highway turnback program.  This project seems to fix the streetscape that is associated with the turnback. 
02
  
Recommended2017-02-17-153ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
Are there any bus stops on the improved areas?  If so, will they also be improved?
Does the Borough have money in their budget for maintenance if project gets approved?
02
  
Recommended2017-04-35-205angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
04
  
Recommended2017-04-40-082lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
04
  
Recommended2017-04-40-123msorbo@pa.govi:0e.t|adfs|msorbo@pa.lcl
04
  
Recommended2017-04-40-134dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Streetscape improvements.  Builds on CFA project awarded last year. 
04
  
Recommended2017-04-40-145djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Appears to be a sound Multimodal project. 
04
  
Recommended2017-04-40-193msorbo@pa.govi:0e.t|adfs|msorbo@pa.lcl
04
  
Recommended2017-04-57-068lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
OK for pedestrian safety and economic development. Again, the application cites the shale gas industry and the impact on infrastructure. Shouldn't that industry play a role in revitalizing local.
04
  
Recommended2017-05-13-044angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
05
  
Recommended2017-05-39-075djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
05
  
Recommended2017-05-39-150ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
05
  
Recommended2017-05-45-053angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
05
  
Recommended2017-05-45-215lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
Preliminary design is just started. Does not address ADA.
05
  
Recommended2017-05-48-114ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
05
  
Recommended2017-06-09-028amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Multimodal project provides safety for pedestrians and access to the Septa bus stop.
06
  
Recommended2017-06-09-104lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
06
  
Recommended2017-06-09-185dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Sidewalk connection that includes ADA upgrades, transit considerations and bike pedestrian amenities.  Municipality to provide local match.  Seems like a well thought out project that will provide necessary connections in a well developed, heavily travelled area.
06
  
Recommended2017-06-09-197ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-15-057msorbo@pa.govi:0e.t|adfs|msorbo@pa.lcl
06
  
Recommended2017-06-23-173dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
No issues with this project.   Sidewalk reconstructions, ADA improvements.  
06
  
Recommended2017-06-46-041dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Phase 1 of trail project that would connect various schools and facilities through trail system.   30% local match from county.   needs environmental permits
06
  
Recommended2017-06-46-050ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-46-060lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
There is only a resolution from the Borough, no letter of support.
Assuming appropriate design, these improvements would make crosswalks ADA compliant.
06
  
Recommended2017-06-46-103amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
Safety improvements that support the university and increase safety between pedestrians and vehicular traffic at an intersection. The dollar amount is relatively low which may be piggybacked with other potential projects.
06
  
Recommended2017-06-46-169lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
Local match is a bank loan.
Investment in pedestrian access appears to be a minimal part of the project.
06
  
Recommended2017-06-46-172ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-46-200ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-46-203ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-67-126lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
06
  
Recommended2017-06-67-139dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Question why this was not included in original trail project from two years ago, but makes sense to have these enhancements.
06
  
Recommended2017-06-67-165dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Bike and Pedestrian path to the navy yard from south Philly.  Check local match for eligibility.  Looks construction of another project for local match requirement. 
06
  
Recommended2017-06-67-184djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Per District 6-0 comments, this project was already awarded $2,020,000 2016 CMAQ money (MPMS 107648); plus $100,000 CFA/DCED money.  Also, there is significant costs for trees, benches, and decorative paving.
06
  
Recommended2017-06-67-186angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
06
  
Recommended2017-06-67-189msorbo@pa.govi:0e.t|adfs|msorbo@pa.lcl
06
  
Recommended2017-06-67-196djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
06
  
Recommended2017-08-22-061msorbo@pa.govi:0e.t|adfs|msorbo@pa.lcl
08
  
Recommended2017-08-36-043djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Appears that this project is in conceptual stage, and not shovel ready.
 
08
  
Recommended2017-08-36-206angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
Project is good pedestrian safety solution; however it is unclear if the project is ready to move forward quickly to construction (ROW and environmental clearances).
08
  
Recommended2017-08-66-026dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Intersection realignment that will improve pedestrian safety.
08
  
Recommended2017-08-66-141angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
08
  
Recommended2017-09-11-017lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
09
  
Recommended2017-11-02-007djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
11
  
Recommended2017-11-02-040dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
very innovative program.  incentivizes personal property owners to improve sidewalks. 
11
  
Recommended2017-11-02-052angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
concerns regarding low cost estimate as indicated by MPO and District reviews
11
  
Recommended2017-11-02-095dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Sidewalk construction and adding turning lanes.  Port Authority providing service so people are traversing...
11
  
Recommended2017-11-02-096ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
11
  
Recommended2017-11-02-110lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
While I recommend the project, the budget and commitment letters are confusing. The budget submitted is for the entire project which is approximately $26 million while the application is for $3 million. The match letters document funding from many local agencies and from the TIGER grants, but I could not identify the funds specifically for this project.
11
  
Recommended2017-11-02-113djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
11
  
Recommended2017-11-02-135angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
11
  
Recommended2017-11-02-192lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
The retaining wall is on Carlow property. If it failed and blocked the sidewalk it would be Carlow's responsibility to clear the sidewalk (same as snow removal).
11
  
Recommended2017-11-02-212ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
11
  
Recommended2017-12-64-118djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
12
  
Recommended2017-12-64-130amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
The pedestrian project will further attract students to the campus. This will positively impact Westmoreland County.
12
collapse Primary Category : Highway/Bridge ‎(49)
  
Recommended2017-01-25-021ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
Is there a way or a need to integrate public transit into this project?
01
  
Recommended2017-01-43-149ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
Operational sustainability-Who will maintain?  Why is this N/A?
Are there bus stops on these streets?  Are the bus stop ADA compliant?
Is a bike lane being proposed? 
Would like a better description about the traffic on these roads (auto, bike, pedestrian and bus). 
01
  
Recommended2017-02-18-221angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
Applicant indicates construction anticipated for Summer 2017. Project is ready to move now regardless of MTF grant funds.
02
  
Recommended2017-02-42-013lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
The shale gas and timbering industries are currently using this road. Much of the deterioration is due to heavy truck use. I understand there are often local agreements with particularly shale gas to restore infrastructure that has been damaged. There does not appear to be any commitment from private industry.
02
  
Recommended2017-03-41-106dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
looks like this is on school property.   repaving and reconstruction.  40% local match obtained from school district capital improvement fund.
03
  
Recommended2017-03-59-158ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
03
  
Recommended2017-04-40-022dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Questions: Looks like this project is turnback from county to locals.  Is there other state funding to support this?  local township has plans to hire staff to maintain once road belongs to them.   30% local match.
04
  
Recommended2017-04-40-089angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
04
  
Recommended2017-04-40-128ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
04
  
Recommended2017-04-40-194djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
04
  
Recommended2017-04-63-038dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
This is a site prep project through industrial park to try to bring more business to Wayne and Pike counties. Project funding matched by eco dev. corporation. 
04
  
Recommended2017-04-65-210angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
bridge project to include multimodal facilities (bike/ped)
04
  
Recommended2017-05-06-010ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
The public transportation impacts are unclear.
05
  
Recommended2017-05-06-016djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
05
  
Recommended2017-05-06-059djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
05
  
Recommended2017-05-06-161djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Appears to be a good project, but question the use of higher priced decorative bricks for cross walks instead of a more cost effective solution.
05
  
Recommended2017-05-45-208dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
road realignment - turning lanes needed for developer project.  Project developer promises local match funding. 
05
  
Recommended2017-05-48-032ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
05
  
Recommended2017-05-53-034lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
However, project is not designed and not ready for construction.
05
  
Recommended2017-05-53-036djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
05
  
Recommended2017-06-09-199djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
06
  
Recommended2017-06-09-201djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
06
  
Recommended2017-06-15-132amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
06
  
Recommended2017-06-15-154ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-15-155djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Per District 6-0, there appear to be some ROW issues that still need resolved.
 
06
  
Recommended2017-06-46-009djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
Was awarded 2014 MTF funding for the design portion of this project; should consider awarding to complete the project.
06
  
Recommended2017-06-46-067lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
06
  
Recommended2017-06-46-151angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
06
  
Recommended2017-06-46-195lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
06
  
Recommended2017-06-67-166ebonini@pa.govi:0e.t|adfs|ebonini@pa.lcl
06
  
Recommended2017-06-67-171dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
This project seems like a good project that would improve multimodal access to a major tourist attraction in Philadelphia.  The technical review does not match the project. 
06
  
Recommended2017-08-01-069lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
Eligible for Municipal Liquid Fuels program funding.
08
  
Recommended2017-08-22-109amccloskey@pa.govi:0e.t|adfs|amccloskey@pa.lcl
The project will help pave the way to attract travelers to stay at a future hotel on HIA property. Also, this will assist with travelers getting to the new Amtrak train station too.
08
  
Recommended2017-08-28-012angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
phase 2 of a previous MTF funded project
08
  
Recommended2017-08-28-202angelwatso@pa.govi:0e.t|adfs|angelwatso@pa.lcl
08
  
Recommended2017-08-36-065lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
Appears to be a good project, but there are two developers which should bear some responsibility.
Most exhibits were in one attachment which made it difficult to be sure that all required documents were provided.
08
  
Recommended2017-08-36-156djbratina@pa.govi:0e.t|adfs|djbratina@pa.lcl
appears to be a well thought out and organized application.
08
  
Recommended2017-09-11-062lcollins@pa.govi:0e.t|adfs|lcollins@pa.lcl
09
  
Recommended2017-09-29-063dspila@pa.govi:0e.t|adfs|dspila@pa.lcl
Rehab of SD bridge. 
09